Sound Testing in Liverpool: What You Need to Know

The essentials on sound testing in Liverpool, from Approved Document E to sign-off.

Liverpool’s residential development pipeline has been busy for years, from city centre apartment conversions around the Baltic Triangle and Ropewalks to new-build housing schemes across Merseyside. Whatever the scale of your project, if you’re creating new dwellings or converting a building into flats, you’ll need to think about sound testing early, not just at the finish line.

Here’s what our Liverpool team gets asked most often, and what you need to plan for.

What is sound testing?

Sound testing, or pre-completion testing, is a requirement of Building Regulations Approved Document E. It measures how well the separating walls and floors between dwellings resist airborne and impact noise, to confirm they meet the acoustic performance standards Building Control needs to see before signing off your development.

Do you need it for you Liverpool Project?

Yes. If you’re creating a new dwelling in Liverpool, whether through new-build housing, a residential conversion, or a change of use, you’ll almost certainly need pre-completion sound testing under Approved Document E, unless the build uses pre-approved Robust Details.

This applies across a range of project types, including:

  • New-build housing and apartment schemes
  • Office, retail or industrial buildings converted to residential
  • Student accommodation and build-to-rent (BTR) developments
  • HMOs and large house-to-flats conversions
  • Care homes and supported living schemes with separate units

Who We Work With

Sound testing brings together a range of people across a project, and we tailor our approach to whoever we’re working with:

  • House Builders: volume and bespoke housebuilders needing reliable, on-programme testing across multiple plots and phases.
  • Property Developers: residential and mixed-use developers who need test results and Building Control sign-off delivered on schedule.
  • Architects & Contractors: technical support at design stage to help specify constructions that pass first time, plus testing once on site.
  • Homeowners: clear, jargon-free guidance for anyone converting a house, loft or basement into a separate dwelling.
  • Project Managers: a single point of contact who keeps testing aligned with the wider build programme, and flags issues early.

Whatever your role on a Liverpool project, our team can slot in at the stage you need us.

How many tests will you need?

As a rule of thumb, one set of tests is required per 10 dwellings. For a development of 10 flats, that means 2 separating wall tests and 2 separating floor tests, covering both airborne and impact sound. If your development uses more than one type of separating construction, you may need additional sets to cover each one.

Getting your site ready

Testing happens at pre-completion stage, once the site is essentially finished aside from minor snagging and decoration. Before booking, make sure:

  • Separating walls and floors, along with internal and external walls, are complete
  • Second fix electrics and plumbing are done
  • All internal and external doors are hung
  • Windows and trickle vents are fitted

The test rooms also need to be quiet and unoccupied, with no other trades working nearby. External groundworks like tarmacking or paving, and internal joinery work, can both interfere with results.

What if a test fails?

It happens, and it’s not the end of the road. Our senior consultants can assess the likely cause from the information available and advise on remedial options. Occasionally a site visit is needed, which may involve opening up ceilings or walls to investigate further, before retesting to confirm a pass.

Turnaround times

Reports and certificates are usually issued within 5–10 working days. If you’re up against a tight programme, we can arrange a same-day or 24-hour turnaround for Liverpool sites, subject to availability.

Why work with an ANC-accredited tester

Peninsular Acoustics is a founder member of the Association of Noise Consultants (ANC) test registration scheme, and every test we carry out is logged on the ANC database with a unique task number.

This means Building Control can independently verify it was completed by a qualified, accredited tester, giving you one less thing to worry about at sign-off.